Project Description

EPC of a 33/150kV 220MVA Substation and a 150kV Transmission Line

  • Engineering ,Design of Civil & Electrical Systems of the substation
  • Permitting from IPTO
  • Supply of HV, MV and LV equipment and materials
  • Construction of concrete bases and steel structures for the equipment of the switchyard
  • Construction of the substation Control Building
  • Erection of the HV equipment / Power Transformer
  • Testing & commissioning
  • Start Up
  • Engineering ,Design of Civil & Electrical Systems for the 150kV Transmission Line
  • Permitting from IPTO
  • Construction and improvement of access roads for the TL
  • Construction of 150kV underground transmission Line
  • Construction of platforms and foundations for steel towers
  • Supply and erection of steel towers
  • Stringing Works
  • Testing & commissioning
  • Start Up