Projects

Construction of 33/150 kV 90/110 MVA substation Oinofyta II, AIS type, construction of HV 150 kV underground interconnection line, new line bay extension in substation Oinofyta I, construction of 50MW/2h BESS plant for the interconnection of 100MWh Battery Energy Storage System to the network

Engineering, Procurement & Construction (EPC) of 33/150 kV 90/110 MVA substation Oinofyta II, Construction of HV 150 kV underground connection line, new line bay extension in substation Oinofyta I, construction of 50MW/2h BESS plant

Location
Oinofyta, Tanagra, Voiotia, Greece
Year
2025
Client
Elsewedy Electric S.A.E.

Project Description

EPC of 33/150 kV 90/110 MVA substation Oinofyta II, Construction of HV 150kV underground connection line, new line bay extension in substation Oinofyta I, construction of 50MW/2h BESS plant

  • Engineering, Design of Civil & Electrical Systems of the substation
  • Engineering, Design of Civil & Electrical Systems of the Battery Energy Storage plant
  • Design, procurement and construction of 150kV cable system
  • Permitting from IPTO
  • Supply of HV, MV and LV equipment and materials
  • Construction of concrete bases and steel structures for the equipment of the switchyard
  • Construction of the substation Control Building
  • Erection of the HV equipment / Power Transformer
  • Construction of concrete bases and steel structures for the BESS and PCS equipment
  • Erection and connection of the BESS and PCS equipment
  • Testing & commissioning
  • Start Up

Other Projects

  • Dervenochoria, Viotia, Greece
  • 2023
  • Iberdrola Group
  • Fyteies, Aetolia-Acarnania, West Greece
  • 2023
  • Energeiaki Koinotita Yperion Syn.P.E.
  • Bekrevenikos, Kozani, Greece
  • 2022
  • Juwi Hellas S.A.