Projects

Construction of 33/150 kV 90/110 MVA extension of Substation Lygeri

Engineering, Procurement & Construction (EPC) of 33/150kV 90/110 MVA extension of Lygeri Substation

Location
Lygeri, Kozani, Greece
Year
2022
Client
C. Rokas SA/ Iberdrola Group

Project Description

EPC of a 33/150kV 90/110 MVA Substation Extension

  • Engineering, Design of Civil & Electrical Systems of the substation extension
  • Permitting from IPTO
  • Supply of HV, MV and LV equipment and materials
  • Construction of concrete bases and steel structures for the equipment of the switchyard
  • Erection of the HV equipment / Power Transformer
  • Testing & commissioning
  • Start Up